Prepare thoroughly for the Agile Business Analysis quiz. Leverage flashcards and multiple-choice questions, each offering hints and detailed explanations. Enhance your knowledge and ensure success in your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is NOT a part of the requirements lifecycle?

  1. Elicitation

  2. Integration

  3. Validation

  4. Management

The correct answer is: Integration

The requirements lifecycle encompasses various stages that are essential for the successful gathering, analysis, and implementation of requirements throughout a project. Elicitation, Validation, and Management are all recognized components of this lifecycle. Elicitation involves gathering requirements from stakeholders through various techniques such as interviews, surveys, workshops, and observation. This stage is critical as it lays the foundation for what needs to be fulfilled. Validation is the process of ensuring that the requirements accurately reflect the stakeholders' needs and are feasible within the project constraints. This stage is vital for confirming that the requirements align with both business goals and user expectations. Management pertains to the ongoing oversight and adjustment of requirements throughout the project’s lifespan. It helps in tracking changes, ensuring priorities are clarified, and maintaining clear communication among stakeholders. Integration, while an important aspect of overall project management and development, is generally not categorized as a specific part of the requirements lifecycle. It refers more to how various project elements come together rather than a discrete stage dedicated solely to managing requirements. Therefore, Integration is recognized as the option that does not fit within the traditional framework of the requirements lifecycle.